Meadowland Boulevard and Westwood Boulevard Intersection Improvements

Traffic to be impacted through August

COLORADO SPRINGS, Colo. – Construction began the first week of June at the intersection of Meadowland and Westwood Boulevards. The closure of the intersection was not expected to last as long as it presently has; however, the discovery of multiple utility conflicts has caused a redesign of the storm sewer alignment, which has extended the project timeline.

Overall construction activities include, but are not limited to:

· Storm sewer installation

· Concrete curb bump out/ADA compliant curb ramps

· Sidewalk/driveway improvements

· Traffic signal upgrades

· Utility relocations

· Mill/overlay intersection

Based on the new timeline, construction completion is expected at the end of August, though the intersection is expected to open Aug. 6. All construction is weather and resource-dependent. Motorists should expect delays and use alternate routes.

leverton

I have been involved with publishing and marketing for the past 32 years. My passion is helping people share their voice. I am able to do this through two important venues: One, with Area-Info.net where people can share everything from opinions to events to news. It is your choice! What do you want to share? Two, through a new program called America's Real Deal I am involved with to help business owners get their voice heard.I schedule speaking engagements with community groups and business groups to share my passion about the importance of "sharing your voice".Contact me directly at lee@leeeverton.coom for scheduling information.

You May Also Like