Keller Haslet Road construction continues through mid-August in Fort Worth

Construction begins July 6 to rehabilitate Keller Haslet Road from Park Vista Boulevard to Alta Vista Road. The roadway will be reconstructed in its present alignment with no additional width or turn lanes added.

The project is a partnership between Tarrant County Precinct 3 and the City of Fort Worth.

Workers will be onsite 8 a.m.-4 p.m. Monday through Friday. The project will be constructed in three phases:

  • Phase 1 will be between Park Vista Boulevard and North Caylor/Harvest Ridge Road. The estimated schedule is July 6-20. Keller Haslet Road and all abutting streets between Park Vista and North Caylor/Harvest Ridge Road will be closed during construction hours. Timberland Boulevard will be used as a detour route.
  • Phase 2 will take place from North Caylor/Harvest Ridge Road to Alta Vista Road. The estimated schedule is July 23-Aug. 3. Keller Haslet Road and all abutting streets will be closed between North Caylor /Harvest Ridge Road and Alta Vista. (Only Hillcrest Estate residents and access to the equestrian facility will be allowed onto the closed portion of Keller Haslet Road). Timberland Boulevard will be used as a detour route.
  • Phase 3 will involve placing a second surface layer of asphalt and backfilling the asphalt edges. Various closures and detours will be in place based on the work location for the day. Estimated project completion is Aug. 17.

Motorists should seek alternate routes or allow extra time for delays when traveling through the construction zone.

To learn more, contact Toby Crabtree at 817-392-5127 or

leverton

I have been involved with publishing and marketing for the past 32 years. My passion is helping people share their voice. I am able to do this through two important venues: One, with Area-Info.net where people can share everything from opinions to events to news. It is your choice! What do you want to share? Two, through a new program called America's Real Deal I am involved with to help business owners get their voice heard.I schedule speaking engagements with community groups and business groups to share my passion about the importance of "sharing your voice".Contact me directly at lee@leeeverton.coom for scheduling information.